10 free, exam-style Physical Security Professional (PSP) practice questions with answers and
explanations. No signup required. Work through them below, then take the
full free PSP practice test to study every exam domain.
These 10 free PSP questions are organized by exam domain, so you can see how each part of the Physical Security Professional blueprint is tested. Reveal the answer and explanation under each question.
Domain 1: Physical Security Assessment 34% of exam
Question 1
On a petrochemical project, the owner provides a geotechnical report showing stable soil conditions. During excavation, the contractor encounters contaminated groundwater not identified in any project documents. Work stops for 14 days while remediation is arranged by the owner. This delay is BEST classified as:
- Non-excusable delay when applied properly
- Excusable, compensable delay under applicable rules
- Concurrent delay in the standard framework
- Excusable, non-compensable delay
Show answer & explanation
Correct answer: B - Excusable, compensable delay under applicable rules
Question 2
The intersection of the Work Breakdown Structure (WBS) and the Organizational Breakdown Structure (OBS) defines which of the following?
- Work package under accepted convention
- Code of accounts in the typical case
- Control account for this purpose
- Cost element as ordinarily interpreted
Show answer & explanation
Correct answer: C - Control account for this purpose
Domain 2: Application, Design, and Integration of Physical Security Systems 35% of exam
Question 3
A project network has four paths:
• Path A: 4 → 6 → 3 → 5 = 18 days
• Path B: 4 → 7 → 8 → 2 = 21 days
• Path C: 4 → 5 → 5 → 4 = 18 days
• Path D: 4 → 9 → 6 → 3 = 22 days
Activity X lies on Path B only. It has an Early Start of day 4 and a duration of 7 days. Its only successor has a Late Start of day 16. What is the Total Float of Activity X?
- 0 days under standard market practice
- 1 day in the standard framework
- 5 days for this purpose
- 4 days for this purpose
Show answer & explanation
Correct answer: C - 5 days for this purpose
Question 4
A project reports the following Earned Value data at month 6:
• BAC = $1,200,000
• PV = $500,000
• EV = $420,000
• AC = $480,000
The project manager believes current cost performance will continue for the remainder of the project. What is the Estimate at Completion (EAC)?
- $1,260,000 in this context
- $1,280,000 in this context
- $1,440,000 under applicable rules
- $1,371,429 under standard market practice
Show answer & explanation
Correct answer: D - $1,371,429 under standard market practice
Question 5
During a forensic schedule analysis, an analyst removes owner-caused delay events from the as-built schedule and recalculates the network to determine what the completion date would have been without those delays. Which Method Implementation Protocol from AACE RP 29R-03 is being applied?
- MIP 3.6 - Impacted As-Planned in the standard framework
- MIP 3.7 - Time Impact Analysis
- MIP 3.5 - Modified/Recreated Update
- MIP 3.8 - Collapsed As-Built in the standard framework
Show answer & explanation
Correct answer: D - MIP 3.8 - Collapsed As-Built in the standard framework
Question 6
A DCMA 14-point schedule health assessment reveals the following results:
• 88% of relationships are Finish-to-Start
• 4% of activities have lags
• 2% of activities have hard constraints
• CPLI = 1.03
Which metric fails to meet the DCMA threshold?
- Relationship Types under accepted convention
- Lags in the typical case
- Hard Constraints in this context
- Critical Path Length Index in the standard framework
Show answer & explanation
Correct answer: A - Relationship Types under accepted convention
Question 7
Activity R has the following three-point duration estimate: Optimistic = 10 days, Most Likely = 14 days, Pessimistic = 24 days. Using the PERT formula, what is the standard deviation of Activity R?
- 3.50 days as ordinarily interpreted
- 2.33 days under applicable rules
- 4.67 days in this context
- 2.00 days for this purpose
Show answer & explanation
Correct answer: B - 2.33 days under applicable rules
Question 8
A scheduler needs to resolve a resource over-allocation on a construction project. The project completion date is contractually fixed and cannot change. Which approach should the scheduler use?
- Resource leveling in this context
- Fast-tracking the affected activities
- Resource smoothing as commonly understood
- Applying mandatory finish constraints
Show answer & explanation
Correct answer: C - Resource smoothing as commonly understood
Question 9
Three activities on the critical path are candidates for crashing:
• Activity E: Normal 12d/$6,000 - Crash 9d/$9,000
• Activity G: Normal 8d/$4,000 - Crash 6d/$5,400
• Activity J: Normal 15d/$10,000 - Crash 12d/$12,400
To reduce the project duration by 2 days at the lowest cost, which activity should be crashed first?
- Activity E in this context
- Activity J under accepted convention
- Activity E and J equally under applicable rules
- Activity G for this purpose
Show answer & explanation
Correct answer: D - Activity G for this purpose
Question 10
A project has a critical path length of 200 working days. The contract required completion date allows 190 working days. What is the Critical Path Length Index (CPLI)?
- 1.05 under applicable rules
- 0.95 as ordinarily interpreted
- 1.00 as ordinarily interpreted
- 0.90 in the standard framework
Show answer & explanation
Correct answer: B - 0.95 as ordinarily interpreted